概述 ········································································································ 1 工程概况 ······························································································ 1 设计依据 ······························································································ 1 设计内容范围和分工 ············································································ 1 本工程主要工作量表 ············································································ 2 工程投资及技术经济指标 ····································································· 2 工程建设方案 ·························································································· 2 线路建设方案 ······················································································· 2 光缆线路路由简述 ················································································ 3 本工程终端方式 ··················································································· 4 路由主要障碍及其处理措施 ································································· 4 光缆进出基站方式 ················································································ 4 光缆设计标准 ·························································································· 5 光缆线路设计基本思路 ········································································· 5 光缆线路设计路由的原则 ····································································· 5 架空光缆线路设计 ················································································ 5 障碍物跨越和设计处理措施 ································································· 8 架空光缆设计 ····················································································· 15 管道光缆设计 ····················································································· 15 墙壁光缆设计 ····················································································· 16 引上光缆设计 ····················································································· 18 局内光缆 ···························································································· 18 光缆防护设计 ····················································································· 19 光缆线路施工规范标准 ·········································································· 21 器材检验 ···························································································· 21 光缆线路复测 ····················································································· 23 立杆 ··································································································· 24
1
2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司
1.4.4 1.4.5 1.4.6 1.4.7 1.4.8 1.4.9
拉线 ··································································································· 24 敷设光缆 ···························································································· 25 光缆的接续与接头盒安装 ··································································· 27 光缆的割接 ························································································ 28 光缆程式及光缆验收标准 ··································································· 30 光缆的预留 ························································································ 31
1.4.10 光缆编制 ···························································································· 33 1.4.11 光缆的分屯及运输 ·············································································· 33 1.4.12 工程竣工及验收 ················································································· 34 1.5
需要说明的其他问题 ············································································· 36
2 预算 ·········································································································· 37 2.1 2.1.1 2.1.3 2.1.4 2.1.5 2.1.6
预算说明 ······························································································· 37 工程概况 ···························································································· 37 预算及技术经济分析 ·········································································· 38 预算编制依据 ····················································································· 38 编制办法 ···························································································· 39 有关费率、费用及单价的取定 ···························································· 39
2.2 预算表格 3 附件
附件一:中铁四局办公楼等综合覆盖系统光缆接入工作量表(共1页) 附件二:2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建
设)勘察设计费汇总表(共1页)
附件三:甲供材料汇总表(共1页) 4 图纸 (1) (2) (3) (4)
桐江大酒店基站-中铁四局办公楼光缆路由施工图 桐江大酒店基站-中铁四局办公楼光缆施工图 翠庭苑光交-投资大厦光缆路由施工图 翠庭苑光交-投资大厦光缆施工图
2
FT20111101-S-SXG-01 FT20111101-S-SXG-02 FT20111102-S-SXG-01 FT20111102-S-SXG-02
2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司
(5) (6) (7) (8) (9) (10) 翡翠路GJ008-出版传媒集团光缆路由施工图 翡翠路GJ008-出版传媒集团光缆施工图 葛大店—枫丹城市花园光缆路由施工图 葛大店—枫丹城市花园光缆施工图 国轩苑基站-国轩苑小区光缆路由施工图 国轩苑基站-国轩苑小区光缆施工图
FT20111103-S-SXG-01 FT20111103-S-SXG-02 FT20111104-S-SXG-01 FT20111104-S-SXG-02 FT20111105-S-SXG-01 FT20111105-S-SXG-02 (11) 翰林府邸光交-翰林府邸2号楼光缆路由施工图 (12) 翰林府邸光交-翰林府邸2号楼光缆施工图 (13) 航林府邸光交接箱-翰林雅居光交接箱路由施工图 (14) 航林府邸光交接箱-翰林雅居光交接箱施工图 (15) 华润置地物业-澜溪镇小区光缆路由施工图 (16) 华润置地物业-澜溪镇小区光缆施工图 (17) 月桂苑基站-月桂苑光交箱光缆路由施工图 (18) 月桂苑基站-月桂苑光交箱光缆施工图
(19) 金笔厂基站-安广科技专修学院南校区光缆路由施工图 (20) 金笔厂基站-安广科技专修学院南校区光缆施工图 (21) 方兴社区基站-锦绣年华光缆路由施工图 (22) 方兴社区基站-锦绣年华光缆施工图 (23) 锦绣社区基站-治安大队主干路由施工图 (24) 锦绣社区基站-治安大队主干施工图 (25) 经济信息中心基站-省光缆路由施工图 (26) 经济信息中心基站-省光缆施工图 (27) 经开区管委会西基站-翰林府邸光缆路由施工图 (28) 经开区管委会西基站-翰林府邸光缆施工图 (29) 翰林府邸2号光缆路由施工图 (30) 翰林府邸2号光缆施工图
(31) 精华职校基站-交通学院南区光缆路由施工图 (32) 精华职校基站-交通学院南区光缆施工图 (33)
康拜基站-汇林园小区光缆路由施工图
3
FT20111106-S-SXG-01 FT20111106-S-SXG-02 FT20111107-S-SXG-01 FT20111107-S-SXG-02 FT20111108-S-SXG-01 FT20111108-S-SXG-02 FT20111109-S-SXG-01 FT20111109-S-SXG-02 FT20111110-S-SXG-01 FT20111110-S-SXG-02 FT20111111-S-SXG-01 FT20111111-S-SXG-02 FT20111112-S-SXG-01 FT20111112-S-SXG-02 FT20111113-S-SXG-01 FT20111113-S-SXG-02 FT20111114-S-SXG-01 FT20111114-S-SXG-02 FT20111114-S-SXG-03 FT20111114-S-SXG-04 FT20111115-S-SXG-01 FT20111115-S-SXG-02 FT20111116-S-SXG-01
2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司
(34) (35) (36) (37) (38) (39) 康拜基站-汇林园小区光缆路由施工图 康拜基站-汇林园小区光缆路由施工图 康拜基站-汇林园小区光缆施工图
莲花路GJ003-华润纺织厂光缆路由施工图 莲花路GJ003-华润纺织厂光缆路由施工图
元一名城C区光交-元一名城A区17#电梯机房光缆路由施工图 FT20111116-S-SXG-02 FT20111116-S-SXG-03 FT20111116-S-SXG-04 FT20111117-S-SXG-01 FT20111117-S-SXG-02 FT20111118-S-SXG-01 (40) 元一名城C区光交-元一名城A区17#电梯机房光缆路由施工图 (41) 龙塘基站-安粮钢材大市场光交箱光缆路由施工图 (42) 龙塘基站-安粮钢材大市场光交箱光缆施工图 (43) 民航家园光缆路由施工图 (44) 民航家园光缆路由施工图
(45) 商旅学校基站-商旅学校光缆路由施工图 (46) 商旅学校基站-商旅学校光缆路由施工图 (47) 文园小区-碧雨新村光缆路由施工图 (48) 文园小区-碧雨新村光缆施工图
(49) 泰格大厦-安徽省教育厅光缆路由施工图 (50) 泰格大厦-安徽省教育厅光缆施工图
(51) 西园环三金寨路GJ002-雅迪商务会所光缆路由施工图 (52) 西园环三金寨路GJ002-雅迪商务会所光缆路由施工图 (53) 香樟花园基站-香樟花园48栋604室光缆路由施工图 (54) 香樟花园基站-香樟花园48栋604室光缆路由施工图 (55) 北金三角基站-新泉家园光缆路由施工图 (56) 北金三角基站-新泉家园光缆施工图 (57) 商务厅基站-省立医院综合楼光缆路由施工图 (58) 商务厅基站-省立医院综合楼光缆路由施工图 (59) 商务厅基站-省立医院综合楼光缆施工图 (60) 邮电学院基站-新华优阁主干光缆路由施工图 (61) 邮电学院基站-新华优阁主干光缆路由施工图 (62)
邮电学院基站-新华优阁主干光缆施工图
4
FT20111118-S-SXG-02 FT20111119-S-SXG-01 FT20111119-S-SXG-02 FT20111120-S-SXG-01 FT20111120-S-SXG-02 FT20111121-S-SXG-01 FT20111121-S-SXG-02 FT20111122-S-SXG-01 FT20111122-S-SXG-02 FT20111123-S-SXG-01 FT20111123-S-SXG-02 FT20111124-S-SXG-01 FT20111124-S-SXG-02 FT20111125-S-SXG-01 FT20111125-S-SXG-02 FT20111126-S-SXG-01 FT20111126-S-SXG-02 FT20111127-S-SXG-01 FT20111127-S-SXG-02 FT20111127-S-SXG-03 FT20111128-S-SXG-01 FT20111128-S-SXG-02 FT20111128-S-SXG-03
2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司
(63) () (65)
邮电学院基站-新华优阁主干光缆施工图 手孔(SK1)主体结构图 手孔(SSK)主体结构图
FT20111128-S-SXG-04
TY-Y-GL-01 TY-Y-GL-01
5
2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司
1 设计说明 1.1 概述 1.1.1 工程概况
2012年第15批综合覆本工程是2012年合肥用户光缆网线路工程一阶段设计:
盖系统接入光缆线路单项工程(铁通合作建设)。本工程共接入中铁四局办公楼、投资大厦、出版传媒集团、枫丹城市花园、国轩苑、翰林府邸2号楼、翰林雅居光交接箱、澜溪镇小区、月桂苑光交箱、安广科技专修学院南校区、锦绣年华、治安大队主干、省、、翰林府邸、翰林府邸2号、交通学院南区、汇林园小区、华润纺织厂、元一名城A区17#电梯机房、安粮钢材大市场光交箱、民航家园、商旅学校、碧雨新村、安徽省教育厅、雅迪商务会所、香樟花园48栋604室、新泉家园、省立医院综合楼、新华优阁主干覆盖等28个接入点。
本工程勘察总长为29.181公里,附挂电力杆路光缆0.979公里,架设架空8芯光缆0.368公里,架设架空12芯光缆0.156公里,架设架空24芯光缆0.611公里,架设架空48芯光缆0.1公里,架设架空72芯光缆0.368公里;敷设8芯管道光缆4.084公里,敷设12芯管道光缆4.588公里,敷设24芯管道光缆5.768公里,敷设48芯管道光缆2.258公里,敷设72芯管道光缆1.205公里;敷设吊线式墙壁光缆16.99百米;管内穿放光缆15.34百米;桥架内明布光缆36.61百米。光缆线路传输长度为33.84公里。
本工程光缆采用ITU-T建议的G.652D光纤,光缆结构为松套层绞式单模光纤光缆。
1.1.2 设计依据
(1) 中国移动通信集团安徽有限公司合肥分公司的《设计委托函》。 (2) 原中华人民共和国信息产业部2010年5月14日发布实施的中华人民共和国通信行业标准 YD 5102-2010《通信线路工程设计规范》。
(3) 原中华人民共和国信息产业部2010年5月14日发布实施的中华人民共和国通信行业标准 YD/T 5121-2005《通信线路工程验收规范》。 (4) 本工程设计实地勘察取得的基础数据和资料。 (5) 建设单位提供的相关资料。 1.1.3 设计内容范围和分工 1.1.3.1 设计内容
1
2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司
(1) 本工程设计内容及范围:2012年第15批综合覆盖系统接入光缆线路工程(铁通合作建设)路由选择、光缆线路敷设安装、技术措施和施工要求及防护设计。
(2) 工程预算编制:工程量统计、工程预算、预算说明等。 1.1.3.2 设计分工
设计以光缆成端接头ODF架为界,光缆成端接头适配器侧(含光纤熔接头、ODF架至设备侧由无线设备安装工程双头尾纤)及光缆线路由本单项工程负责,负责。
1.1.4 本工程主要工作量表
表1.1-1 本工程主要工程量表
序号 1 2 3 4 5 6 7 8 9 10 11 工 作 项 目 电力杆路光缆 架空光缆(8芯) 架空光缆(12芯) 架空光缆(24芯) 架空光缆(48芯) 架空光缆(72芯) 管道光缆(8芯) 管道光缆(12芯) 管道光缆(24芯) 管道光缆(48芯) 管道光缆(72芯) 吊线式墙壁光缆 管内穿放光缆 桥架内明布光缆 单位 公里 公里 公里 公里 公里 公里 公里 公里 公里 公里 公里 百米 百米 百米 数量 0.979 0.368 0.156 0.611 0.1 0.368 4.084 4.588 5.768 2.258 1.205 16.99 15.34 36.61 备 注 1.1.5 工程投资及技术经济指标
工程预算总投资和单位线路公里造价见下表:
表1.1-2 工程预算总投资和单位线路公里造价表
项 目 光缆线路长度 总投资 单位造价 单位造价 单 位 公里/纤芯长度 元 元/线路公里 元/芯公里 指 标 33.84/590.042 904398.5 26725.72 1532.77 本单项工程预算总投资904398.5元,光缆线路纤芯总长度为590.042芯公里。 1.2 工程建设方案 1.2.1 线路建设方案
2
2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司
1.2.1.1 线路网络组成
本工程综合覆盖系统接入点均接入至所属基站。2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)。 1.2.1.2 光缆敷设方式
本期工程接入光缆主要采用管道方式和附挂电力杆路、墙壁吊线方式敷设。1.2.2 光缆线路路由简述
根据建设要求,设计进行了详实的实地勘察后,选定本工程光缆线路路由, 现将本工程接入段路由分段简述如下: 序 号 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 综合覆盖系统接入点 接入基站 光缆芯数(芯) 24 8 8 12 12 12 48 24 48 8 8/12 24 24 8/12/72 72 长度 (公里) 0.78 0.4 1.45 1.61 0. 0.87 1.1 0.13 0.3 0.35 0.9/2.2 1.2 0.35 1.75/0.5/0.7 1.5 区域 中铁四局办公楼 投资大厦 出版传媒集团 枫丹城市花园 国轩苑小区 翰林府邸2号楼 翰林雅居光交箱 澜溪镇小区 月桂苑光交箱 安广科技专修学院南校区 锦绣年华 治安大队 省 翰林府邸 交通学院南区 桐江大酒店 翠庭苑光交 翡翠路GJ008 葛大店 国轩苑 翰林府邸光交箱 翰林府邸光交箱 华润置地物业 月桂苑 金笔厂 方兴社区 锦绣社区 经济信息中心 经开区管委会西 精华职校 3
包河区 政务区 政务区 包河区 蜀山区 经开区 经开区 蜀山区 包河区 庐阳区 经开区 经开区 包河区 经开区 包河区
2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司
16 17 18 19 20 21 22 23 24 25 26 27 28
汇林园小区 华润纺织厂 元一名城A区17#电梯机房 安粮钢材大市场 名航家园 商旅学校 碧雨新村 安徽省教育厅 雅迪商务会所 香樟花园48栋604室 新泉家园 省立医院综合楼 新华优阁 康拜 莲花路GJ003 元一名城C区光交 龙塘 商旅学校 文园小区 泰格大厦 喜欢环三金寨路GJ002 香樟花园 北金三角 商务厅 邮电学院 8/24/72 24 24 12 12/24 8 12/24 8 8 24 12/24 8/12/48 0.45/0.55/0.95 2.45 1.15 0.4 2.6/0.4 0.85 0.25/0.5 0.7 0.45 0.65 0.3/0.8 0.3/0.2/0.75 经开区 经开区 瑶海区 肥东 包河区 庐阳区 蜀山区 庐阳区 庐阳区 蜀山区 庐阳区 包河区 8/12/24/48 0.2/0.55/0.25/1.3 蜀山区 1.2.3 本工程终端方式
光缆在移动机房内综合机柜ODF子框或光缆终端盒及光缆配线箱进行成端接续。
1.2.4 路由主要障碍及其处理措施
本工程主要选择管道、墙壁吊挂、以及利用供电杆路敷设光缆。工程中光缆
线路沿线大部分线路障碍为小区等,对于架空线路一般没有太大的影响。 1.2.5 光缆进出基站方式
本工程均采用利用原有管道或利用供电杆路架空方式敷设进入基站,尽量采用管道方式敷设,应在适当位置悬挂光缆标志牌,以区分光缆接入的区段、光缆芯数、建设时间,便于光缆的维护。
4
2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司
1.3 光缆杆路设计标准 1.3.1 光缆线路设计基本思路
(1) 光缆线路网的设计,在全面规划的基础上,设计考虑相应满足年限的需要,考虑与下期工程相结合,根据今后传输网覆盖和节点的属性,确定本工程的光缆容量和路由、电杆程式,达到本期及后续的扩建工程技术经济合理。 (2) 光缆线路网设计应考虑传输网的整体性,具有一定的通融性,安全灵活,投资节省,适应基站的发展和变动,在城市中心区域则需要注意路由的环境美化,实施光缆线路的隐蔽性或埋入地下。
(3) 光缆线路建设应保持相对稳定,要积极采用新技术、新设备、降低成本,满足各种新业务的要求。
(4) 接入网线路设计,应对基站发展需要的纤芯和时间进行分析,通过各种技术措施使该网络构成一个可以调度灵活,纤芯使用率高、投资节省、便于发展、利于营运维护的网络。 1.3.2 光缆线路设计路由的原则 (1) 考虑传输网络系统的整体性。
(2) 光缆线路路由短捷、安全性、投资经济性、并考虑施工及维护方便。 (3) 对可利用的原有线路资源充分而又合理地利用实施新建工程。
(4) 设计光缆路由选择了避开有化学和电气腐蚀的地区。不可避免时,设计将作化学分析和电蚀测量,以便采取必要的防护措施。
(5) 光缆路由设计考虑避免与高压输电线路、电气化铁道长距离的平行接近。在受到环境不可避免时,应进行测量和计算强电对通信线路危险影响和干扰影响,其不得超过相关标准的规定。 1.3.3 架空光缆线路设计 1.3.3.1 架空光缆线路
(1) 架空光缆线路杆路的杆间距离,应根据地形情况、线路负荷、气象台条件以及将来发展扩建的要求等因素来确定。一般情况下,郊区和郊区以外的地方杆间距离以50米为宜,但应避免小于30米的杆距,城区则根据道路及建筑物的实际情况确定杆距。
(2) 架空光缆线路负荷区划分,是根据平均十年出现一次最大的缆线上冰凌厚度和结冰时最大风速、最低气温等气象条件为依据的,划分标准如下:
5
2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司
表1.3-1 架空电缆线路负荷区划分表
负 荷 区 别 气 象 条 件 缆线上冰凌等效厚度(mm) 结冰时温度 结冰时最大风速(m/s) 无冰时最大风速(m/s) 轻负 荷区 ≤ 5 -5℃ 10 25 中负 荷区 ≤ 10 -5℃ 10 / 重负 荷区 ≤ 15 -5℃ 10 / 超重 负荷区 ≤ 20 -5℃ 10 / 注:① 冰凌的密度为0.9g/cm³,如果是冰霜混合体,可按其厚度的二分之一折算为冰厚。 ② 最大风速应以气象台自动记录10 分钟的平均最大风速为依据。 ③ 根据上表的划分,本工程按属中负荷区考虑。 ④ YD5137-2005《本地通信线路工程设计规范》表2.3.2 (3) 本设计计算钢绞线及电杆强度时遵循以下安全系数的规定: ① 当钢绞线用作普通吊线及双吊线中的正吊线时,安全系数不得小于3,当钢绞线用作双吊线中的辅助吊线时,安全系数不得小于2。
② 架空电缆线路,各种程式的拉线,安全系数不得小于3。 ③ 钢筋混凝土电杆的安全系数不得小于2。
(4) 杆路上加挂的光缆吊线普通杆距吊线程式设计按照下表规定执行:
表1.3-2 普通杆距架空电缆吊线规格表
负荷区别 中负荷区 中负荷区 杆距L(m) 电缆重量W(kg/m) 吊线规格线径 (mm)×股数 2.2×7 2.6×7 3.0×7 L≤ 40 W≤ 1.82 40 ② 线路偏转角大于45°时(角深大于19.46m),应设双顶头拉线。 ③ 架空光缆长杆档(杆距在100m~150m时)应设斜力拉线,长杆档杆距大于150m时应设置7/2.6辅助吊线,并设置三方拉线,当杆距超过250米时宜设置H杆跨越装置。 ④ 顶头拉线采用比电缆吊线的规格大一级的钢绞线。 ⑤ 城市、乡镇、村庄建筑物或路边上的拉线应装设醒目的拉线警示管。 6 2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司 (6) 架空电缆线路不宜与电力线路合杆架设;但在不可避免时,允许和10kV 以下的电力线路合杆架设。但必须采取相应的技术防护措施,并与有关方面签订协议。与10kV 电力线合杆时,电力线与通信电缆间净距不应小于2.5m,且移动光缆应架设在电力线路的下部。 (7) 架空线路设备应根据有关的技术规定进行可靠的保护,以免遭受雷击、高电压和强电流的电气危害,以及机械损伤。架空线路与其它设施接近或交越时,其间隔净距应符合下表规定。 表1.3-3 架空通信线路与其他设施的空距与隔距(单位:m) 其他设施名称 最小水平净距 备 注 1.0 消防栓 消防栓与电杆间的净距 0.5~1.0 地下管.线 包括通信管线与电杆间的净距 火车轨道 地面杆高的4/3倍 公 路 不小于1h h为地面上电杆高度(m) 0.5 人行道边石 地面上已有其他杆路 其他杆高的4/3倍 地面杆高 0.5 市区树木 2.0 郊区树木 2.0 房屋建筑 至房屋建筑的水平净距 YD 5137-2005《本地通信线路工程设计规范》表2.3.12-1 表1.3-4 架空光缆架设高度表(单位:m) 名称 市区街道 市内胡同里弄 铁路 公路 土路 房屋建筑 河流 市区树木 郊区树木 其他通信导线 与线路平行平行时 垂直净距 4.5 4.0 3.0 3.0 3.0 备注 最低线缆到地面 最低线缆到地面 最低线缆到地面 最低线缆到地面 最低线缆到地面 与线路交越时 垂直净距 5.5 7.5 5.5 5.0 5.0 0.6 1.5 1.0 1.5 1.5 0.6 备注 最低线缆到地面 最低线缆到地面 最低线缆到地面 最低线缆到地面 最低线缆到地面 最低线缆到距脊 最低线缆到房屋平顶 最低线缆到最高 水位时船桅顶 最低线缆到树枝的垂直距离 最低线缆到树枝的垂直距离 一方最低线缆线 到另一方最高线条 与同杆已有 0.4 缆线到缆线 缆线间隔 YD 5137-2005《本地通信线路工程设计规范》表2.3.12-2 7 2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司 表1.3-5 架空光缆交越其他电气设施的最小垂直净距表 最小垂直净距(m) 其他电气设施名称 10kV以下电力线 35~110kV电力线 大于110~154kV电力线 大于154~220kV电力线 供电线接户线 霓虹灯及其铁架、变压器 有轨、无轨电车滑接线 架空电力线路有 防雷保护设备 2.0 3.0 4.0 4.0 架空电力线路无 防雷保护设备 4.0 5.0 6.0 6.0 备 注 最高缆线到电力线条 最高缆线到电力线条 最高缆线到电力线条 最最高缆线到电力线条 0.6(注1) 1.6 1.25(注2) YD 5137-2005《本地通信线路工程设计规范》表2.3.12-3 注:1 通信线路应架设在电力线路的下方位置,应架设在电车滑车线的上方位置。 2 注1《本地通信线路工程验收规范》备注为带绝缘层的间距,本设计执行《本地通信线路工程验收规范》规定。 3 注2《本地通信线路工程验收规范》备注为通信线路不允许架空交越,本设计执行《本地通信线路工程验收规范》规定。 1.3.4 障碍物跨越和设计处理措施 1.3.4.1 河流、桥梁 光缆线路在通过两堤间大于150m河流或较大的沟渠时,宜采用桥上敷设的方式,较小的河流亦可采用架空跨越或微控定向钻孔方式穿越。但微控定向钻孔实施位置必须符合水务部门有关防汛的规定。钻孔位置应距离堤坝不小于50米,同时钻孔在河床最低点和河床最深处最小间距应大于2米。如河床地势平缓(有足够的空间),也可考虑在堤内进行定向顶管。如果穿越点的河流或沟渠附近有桥时,应当首选在桥上敷设的方式为宜。在桥上应当采用管道或吊线敷设的方式,并应采取适当的保护措施。当在桥上敷设光缆有困难,或线路需迂回绕道时增加较大投资时,也可在技术经济合理条件下,采用水底光缆的敷设方式。 1.3.4.2 公路、铁路 光缆线路和铁路、高等级公路交越通过时,宜采取微控定向钻孔敷设方式;如和县道或县道以下的道路交越时,一般可采用架空交越的通过敷设方式。但要保证跨越杆位的确定(符合公路法规定的隔距)、电杆程式的保证(要求预留第二层光缆吊线位置后与地面的空距),以保证线路架设后要符合施工验收规范要求和相关路政部门的规定要求。 8 2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司 1.3.5.1 组装电杆及立杆 (1) 本工程设计的电杆为环形预应力混凝土电杆,标准杆高为7.0m,稍径为150mm,跨越公路、铁路、较大的水塘等时将采用8m以上的电杆(以保证吊线距跨越公路、铁路、距地面高度不小于规定的高度)。为保证杆路的美观,设计要求应对跨越障碍段落的电杆进行配高。 (2) 设计对角杆、分线杆、跨越杆、直线线路中有双方、四方拉的电杆都设置了拉线式地线,对本工程线路在与10kV的高压输电线交越的两侧电杆设置避雷线;对了解到曾受雷击地区的电杆加装了避雷线。 (3) 设计要求立杆前应对电杆长度、规格是否符合施工图设计的规定要求进行核实,立杆前应检查杆洞的深度是否符合设计规定的要求。如发现问题应及时修正直至合格。对设计图纸指定有水泥底盘的电杆,则须按设计规定先把底盘置入杆洞底部,并要求杆根必须置放在底盘上。 (4) 直线线路的电杆位置应在线路路由的中心线上。电杆中心线与路由中心线的左右偏差应不大于50mm;电杆本身应上下垂直。 (5) 设计规定角杆必须在线路转角点内移,水泥电杆的角杆应立在线路转角点以内100~150mm的位置上,木杆应内移200~300mm,以保证角杆立起后,杆梢应在线路转角点以外,才能使线路吊线收紧后再回到转角原点上,设计对因地形或加装撑杆的角杆可不内移;终端杆立起后,杆身应向张力的反侧倾斜10~200mm,以便在收紧吊线后接近垂直,但不得有向内倾的现象。 (6) 设计要求角杆的测量中禁止有“S”弯,两反向角杆要求至少有一根直线杆,但在线路跨越公路铁路河流时要求至少保持2根直线杆。 (7) 电杆入洞后,经看正扶直后,应立即分层回土(每回土300mm)夯实,市区立杆,杆根回土后应培土50~100mm,在有路面的路上立杆,杆根不宜培土,但应与路面平齐,其他地段应将回填土培在电杆根部周围,一般高出地面100~150mm。 (8) 设计对负荷较大的电杆或土质松软地方的电杆加装水泥杆卡盘或底盘,具体位置详见各施工图纸。 (9) 设计对穿越高等级公路时采取顶管过路的方式通过,在穿越铁路时可采取寻求公铁路立交的过路桥涵穿越,对寻求立交的过路桥涵通过,其距线路路由较远时,则采取了顶管过铁路的方式穿越;设计对穿越较大河流或跨越其他障碍 9 2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司 时,在杆距大于150m时,采取了辅助吊线或采用大于原吊线程式的敷设方式。 (10) 设计中长杆档设计一般用于水面、河流等特殊地点,除设计图纸中指明处外,一般应避免新增100m以上的长杆档,对150m以上的长杆档需设置三方拉线。 (11) 设计允许个别地点由于地形的,杆位可适当偏离线路,但要求偏离距离不得超过1m,此杆吊线可用偏担装置支撑。 (12) 水泥电杆的埋深设计规定按下表执行。 表1.3-6 水泥电杆洞深表 土 洞 深 程质 m 1.30 1.40 1.60 1.70 1.80 1.90 2.2 0.80 1.00 1.20 1.40 1.60 1.80 2.00 普通土(m) 硬土(m) 水田、湿地(m) 石质土(m) 式 6.0 1.20 1.00 7.0 1.30 1.20 8.0 1.50 1.40 9.0 1.60 1.50 10.0 1.70 1.60 11.0 1.80 1.80 12.0 2.10 2.0 YD / T 5138-2005《本地通信线路工程验收规范》表3.1.1 (13) 地线、避雷线设计 ① 水泥电杆有预留避雷线穿钉的,应从穿钉螺母向上引出一根4.0mm线径的钢线并应高出电杆顶100mm;无预留避雷线穿钉的,应从电杆中穿放一根4.0mm线径的钢线,并伸出电杆顶部100mm,电杆梢部的水泥封堵穿放避雷线后应重新封堵;有拉线的电杆也可利用拉线做避雷线。 ② 在与10kV以上的高压输电线交越处的两侧应装置避雷线,该避雷线应采用放电间隙式的装置。 ③ 避雷线的地下延伸部分应埋在离地面700mm以下,延伸线的接地电阻要求及参考延伸长度见避雷线接地电阻及延伸线参考长度表。如由特殊要求时可按设计规定办理,避雷线也可采用地线棒接地。避雷线和地线棒的连接应牢固,设计要求其连接为焊接或螺栓固定的方式。地线延伸线严禁盘成圈,但可“蛇行”延伸。地线避雷线都应在电杆较隐蔽侧敷设。 10 2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司 表1.3-7 避雷线接地电阻及延长线参考长度表 一般避雷线要求 与10kV输电线交越杆避雷线要求 电阻(Ω) 延伸(m) 电阻(Ω) 延伸(m) 80 1.0 25 2 沼泽土 80 1.0 25 3 黑土地 100 1.5 25 4 粘土地 150 2.0 25 5 砂粘土 200 5.0 25 9 砂土 YD / T5138-2005《本地通信线路工程验收规范》附录C 注:避雷装置详情请见架空杆路避雷装置示意图 土质 1.3.5.2 拉线 (1) 本工程设计拉线程式一般为7/2.2与7/2.6,线路偏转角大于45°(角深为19.46m)时,应装设双终端拉线。 (2) 一般地锚出土长度为300mm,三条双下地锚出土长度为400~500mm,允许偏差50~100mm。地锚钢柄长度规格根据设计埋深要求选定。埋设拉线地锚铁柄的出土斜槽,应与拉线上把成直线,不得有杠、顶现象。 (3) 高桩拉线的副拉线、拉线中心线、正拉线、电杆中心线应成直线、其中任何一点的最大偏差应≤50mm。吊板拉线的拉线抱箍至八线担之间的间距不得小于地面杆高的五分之一。 (4) 设计对吊板拉线制作规格要求应符合YD/T5138-2005“本地通信线路工程验收规范”中的3.4.13的要求。 (5) 墙壁拉线的拉攀距墙角应≥250mm,距屋沿≥400mm。 (6) 装设撑杆的埋深不应小于600mm,距高比应不小于0.5。撑杆的装设位置应在光缆吊线下的100mm处。撑杆与水泥杆的接合规格应符合YD/T5138-2005 “本地通信线路工程验收规范”中的3.5.1-2的要求。 (7) 在直线段杆档超过14档时,应选择适当位置设抗风拉线(侧拉线),拉线程式为7/2.2;在直线段杆档32档时,应选择适当位置设置四方拉(顺线拉和侧拉),拉线程式为7/2.6与7/2.2。 (8) 侧拉拉线的抱箍应设在吊线抱箍下的150mm处,顺线拉线由于吊线需做假终结,因此其抱箍应设在吊线抱箍的上方的250mm处以内,以方便假终结的设置。 (9) 拉线制作安装应符合规范要求。设计对上、中把均按夹板法考虑。 11 2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司 (10) 拉线地锚的埋深,设计要求施工要符合表1.3-8的规定,拉线与地锚铁柄程式的配合请按表1.3-9的规定执行。 (11) 撑杆是替代拉线的平衡线路张力或合力的一种装置,撑杆应设在线路合力或张力的同侧。撑杆一般埋深应为600mm,撑杆的距高比宜为0.6以上,最小应不小于500mm。 (12) 墙壁拉线的拉攀距墙角应不小于250mm,距房檐不小于400mm。 (13) 市区、乡镇、公路边的拉线设计均加装PVC斜拉线警示管(Φ34mm每处2m)。 表1.3-8 地锚洞深表 洞 土 深 质 m 1.4 1.5 1.6 1.7 1.9 2.0 2.3 1.0 1.1 1.2 1.3 1.4 1.5 1.7 普通土(m) 硬土(m) 水田、湿地(m) 石质土(m) 式 7 / 2.2 1.3 1.2 7 / 2.6 1.4 1.3 7 / 3.0 1.5 1.4 2×7 / 2.2 1.6 1.5 2×7 / 2.2 1.8 1.7 2×7 / 2.2 1.9 1.8 2.0 2.0 V型7 / 3.0 YD / T 5138-2005《本地通信线路工程验收规范》表3.4.6 程表1.3-9 水泥拉线盘及地锚柄程式表 序 号 1 2 3 拉线程式 7/2.2 7/2.6 7/3.0 水泥拉线盘程式(mm) 500×300×150 600×400×150 600×400×150 拉柄直径(mm) 16 20 20 20 20 22 22 备 注 2条或3条合用一个地锚时的规格 4 2×7/2.2 600×400×150 5 2×7/2.6 700×400×150 6 2×7/3.0 800×400×150 7 1000×500×300 V型2× 7/3.0 YD / T 5138-2005《本地通信线路工程验收规范》表3.4.7 注:一般地锚出土长度应为300mm,允许偏差小于50~100mm 1.3.5.3 号杆 (1) 号杆一般应按由北向南或由东向西顺序编号,本设计按接入环杆路的A-B端进行编号,详情请看各段施工图纸。 12 2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司 (2) 杆路沿公路、铁路或乡村大道边时,杆号应写在靠近道路的一侧,如两边都有道路,应以杆路靠近所沿着的道路为准。如果杆路不沿道路建设时,如有小路则面向小路编号,或面向维护人员便于行走的一侧编号。 (3) 号杆的字或牌的高度:最末一个字或号牌下边缘应距地面2.5m。杆号规20cm的底漆面,编号为黑色字体,杆号应面向公路或人行道路。 定喷刷白色60× (4) 在同一个段落内,应采取同一种书写样式或钉牌。 1.3.5.4 架空吊线 (1) 光吊线布放前,应装好双吊线抱箍,抱箍的程式要和电杆外径相配,吊线应用三眼单槽夹板固定于电杆的吊线抱箍或安装吊线的线担上。 (2) 吊线夹板距电杆的顶部的距离应符合设计要求。在一般情况下吊线夹板距点杆顶的距离应≥500mm,在特殊情况下应≥250mm。吊线抱箍在各电杆上的位置,宜距地面等距,所挂吊线有坡度变化时,一般不宜超过杆距的2.5%,由于地形也不得超过杆距的5%。 (3) 设计要求杆路上架设第一条吊线时,应设在杆路的车行道反侧或建筑物侧。 (4) 设计规定在同一杆路架设2层吊线时,两吊线的间距为40cm。 (5) 吊线在电杆上的安装位置,应能保证架挂光缆后在最高温度或最大负荷时其垂度与地面的最小净距必须符合表1.3-10的要求。 (6) 布放架空吊线时,应切实注意钢绞线不要受外力的损伤。放线时发现有损伤的线段,应将其剪掉重新接头后再进行架挂,以保证施工质量和安全,布放吊线应尽量使用整盘钢绞线,以减少中间接头。新设吊线在任何情况下一个杆档内只允许有一个接头。 (7) 布放架空吊线前,应将整盘钢绞线放置在放线车(架)上,转动放线车(架)上的转盘,即可将吊线放出。根据施工现场情况,可将吊线放在电杆和夹板中间的穿钉进行布放,在宽阔无障碍的地方,亦可将吊线先在地上放开,然后托上电杆,但不可使吊线受损或妨碍交通。 (8) 设计要求一个段落上吊线在电杆上的左右位置(杆面程式)应保持一致。吊线在终端杆及角深≥ 19.46m(转角角度≥ 45º)的角杆均应做终结,角深在5~10m时应加装4.0钢线缠绕的吊线辅助装置,角深在10~15m时应加装同吊线程式一样的钢绞线辅助装置。 13 2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司 (9) 本设计对吊线的接续一律采用夹板法制作,如施工采用缠绕法,则要求两端必须一致。 (10) 设计要求光缆吊线必须置于吊线夹板的线槽中;夹板线槽必须置于上方;直线杆夹板唇口应向电杆或支持物,角杆的夹板唇口应背向吊线的合力;固 定吊线夹板的穿钉螺母应在夹板侧,螺母外露的丝扣应不小于1cm,不大于5cm。(11) 设计对光缆吊线坡度变更超过杆距的5%小于10%的时候,要求应制作仰俯吊线辅助装置。 (12) 设计对两条吊线交叉时,吊线高度差在400mm以内时,要求做成十字吊线。具体规定为两条吊线程式相同时,主干吊线应置于交叉的下方;两条吊线程式不同时,吊线程式大的应置于交叉的下方。夹板法十字吊线的规格应符合YD/T5138-2005《本地通信线路工程验收规范》3.8.10的要求。 (13) 夹板法丁字结、卡接法丁字结和缠绕法丁字结及双吊线法丁字结的规格设计要求应符合YD/T5138-2005《本地通信线路工程验收规范》3.8.11的规定。 (14) 收紧吊线应根据吊线张力大小以及施工地点、工具配备情况,采取适当的方法收紧吊线,一般情况下用绞盘收紧比较简单易行。 (15) 每段吊线紧线档数最多不得超过20个杆档。如遇角杆较多或吊线坡度变化较大时,可适当减少紧线档数。在收紧吊线过程中,应避免碰触电力线或其他建筑物,以保证施工安全。收紧吊线以后,应保证各杆档间吊线的张力垂度保持均匀,并对因收紧吊线发生的电杆歪斜进行扶正,保证线路的美观。 (16) 跨越通航河流和公路时,设计在适当位置设了禁止抛锚的标志牌以及带有荧光效用的过路警示标志。过路标志牌在夜间具有夜光、反光警示作用。 (17) 本工程设计按中负荷区考虑架空光缆吊线的垂度,见表1.3-10。 表1.3-10 中负荷区吊线原始垂度标准 吊线程式 可悬挂电缆重量 W(kg/m) 垂 杆 度 mm距 30 m 气 o 温 C -10 38 0 42 10 48 20 54 7/2.2 W=1.32 W=1.224 W=3.02 7/2.6 W=1.82 35 59 67 77 90 40 99 115 137 167 45 96 108 123 143 14 50 140 160 187 223 30 41 46 52 61 35 63 72 83 98 40 108 128 154 190 45 93 104 118 136 50 133 152 176 207 2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司 吊线程式 可悬挂电缆重量 W(kg/m) 7/2.2 W=1.32 W=1.224 W=3.02 7/2.6 W=1.82 垂 杆 度 mm距 30 35 40 45 50 30 m 气 温 oC 30 63 108 209 168 270 72 40 76 133 2 204 330 87 YD/T 5138-2005《本地通信线路工程验收规范》附录H.0.3 35 118 147 40 239 297 45 159 191 50 246 300 1.3.4 架空光缆设计 (1) 本设计对光缆挂钩的间距要求为500mm,允许偏差±30mm,光缆在电杆两侧的第一只挂钩应各距电杆400mm,允许偏差±20mm。本工程选用25mm挂钩,对同吊线敷设3条以下光缆的都采用25mm挂钩。在进局段落,距离较短而条件不允许再新增设吊线的情况下,同吊线敷设3条光缆则采用35mm挂钩。 (2) 架空光缆应按本设计要求的A、B 端敷设,敷设时光缆的曲率半径应大于其外径的20倍。 (3) 架空光缆敷设后应自然平直并保持不受拉应力、无扭转、无机械损伤。 (4) 本工程设计根据省公司网络部2007年9月的规定:轻负荷区光缆每3~5根电杆作一处预留,预留在电杆两侧的挂钩间下垂25~30厘米,预留宽度一般2米,并套塑料套管保护。光缆经十字吊线或丁字吊线处也应安装塑料套管保护。详见通用图TY-Y-GL-01。 (5) 架空光缆接头及余缆在吊线及电杆上吊扎、固定的规定应符合通用图TY-Y-GL-01的要求 (6) 架空光缆在丁字吊线处吊扎的规定应符合通用图TY-Y-GL-01的要求。 1.3.5 管道光缆设计 (1) 设计规定敷设管道光缆前必须清刷管孔 ,敷设的孔位应符合设计规定。 (2) 设计对孔径大于等于Φ110mm的管道孔内敷设光缆时,考虑敷设了4根子管(材料预算按不同色考虑),本工程设计子管规格为Φ28/32mm。子管要求超出子管手孔壁150~200mm。本设计要求对穿放光缆的子管管孔应进行封堵。如是梅花管的,只要剪去本工程占用的一孔堵头,须再将其他堵头继续堵住未占用管孔,以免泥砂入内影响以后使用。 (3) 设计要求子管在管道中间不得有接头。 15 2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司 (4) 应按设计规定的A、B端敷设光缆,敷设光缆的最大牵引力应小于光缆的最大拉力。一般情况下敷设光缆时的牵引力应小于光缆允许拉力的80%。敷设管道光缆可使用石蜡油、滑石粉作为光缆的润滑剂,严禁使用有机油脂。 (5) 敷设管道光缆的曲率半径必须大于光缆外径的20倍。以人工方法牵引敷设光缆时,应在人孔内逐段接力牵引,在直线段每个人(手)孔应安排一个施工人员,在拐弯人(手)孔安排2~3个施工人员,作为辅助牵引。光缆绕“∞”字敷设时,其内径应不小于2m。敷设后的光缆应平直、无扭转、无明显刮痕和损伤。其留长应符合设计要求。管道光缆的固定后曲率半径必须大于光缆外径的10倍。 (6) 敷设后的光缆应紧靠人(手)壁,并用扎带扎于托架托板上。光缆固定后应按设计要求封堵光缆管孔,并及时栓挂光缆标志牌或光缆接头标志牌。管道光缆的标识牌,考虑维护的便利,规定每个手孔在光缆的两端都设置光缆标志牌,如该手孔有预留光缆,则预留处也应设置标志牌。标志牌应标出预留长度(根据光缆的尺码标记标出)。本设计规定对光缆在人(手)孔内子管外的部分均采取加套波纹塑料管保护措施。 (7) 人(手)孔内光缆接头每侧留长为6~10m盘留光缆,人(手)孔内的光缆接头必须顺向安装在人(手)孔正上方的光缆接头盒托架上,接头余缆应紧靠人(手)孔壁或搁架,盘成O型圈,内径大于0.6m,并以扎带绑扎在电缆托板上,并应符合下列要求: ① 应尽量安装在人(手)孔内较高的位置,避免雨季时受到人(手)孔内积水的浸泡。 ② 安装位置应不影响人(手)孔其他光缆的接头安装。 (8) 光缆出管孔150mm以内不应做弯曲处理。 (9) 管道光缆每500m预留应不少于10m。 (10) 设计对管道光缆中间接头的加强件不要求做电气连接,接头盒在手孔内要安装牢固。 (11) 每个人(手)孔内光缆在孔内的A-B方向和预留光缆的最高处,应挂有光缆标志牌以便于维护查验。 1.3.6 墙壁光缆设计 (1) 沿建筑物敷设应横平竖直不影响房屋建筑美观。路由选择不应妨碍建筑 16 2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司 物的门窗启闭,电缆接头的位置不应选在门窗部位。 (2) 安装电缆位置的高度应尽量一致,墙壁光缆离地面高度应≥ 3m,跨越街坊、院内通路等应采用钢绞线吊挂,其缆线最低点距地面应符合YD/T5138-2005《本地通信线路工程验收规范》附录F的要求。 (3) 应避开高压、高温、潮湿、易腐蚀和有强烈振动的地区。如无法避免,应采取保护措施。 (4) 应避免选择在影响住户日常生活或生产使用的地方。 (5) 应避免选择在陈旧的、非永久性的、经常需修理的墙壁。 (6) 墙壁电缆应尽量避免与电力线、避雷线、暖气管、锅炉及油机的排气管等容易使电缆受损害的管线设备交叉与接近。 (7) 进局光缆作墙壁吊线敷设时应按设计要求的A、B端敷设墙壁光缆。 (8) 不宜在墙壁上敷设铠装或油麻光缆。 (9) 墙壁光缆与其他管线的最小间距应符合表1.3-11的规定。 表1.3-11 墙壁光缆距其他管线的最小距离表 管线种类 电力线 避雷引下线 保护地线 热力管(不包封) 热力管(包封) 给水管 煤气管 电缆线路 平行净距(mm) 200 1000 200 500 300 150 300 150 交越净距(mm) 100 300 100 500 300 100 100 100 (10) 吊线式墙壁光缆使用的吊线程式应符合设计要求。墙上支撑的间距应为8~10m,终端固定物与第一只中间支撑的距离不应大于5m。 (11) 吊线在墙壁上的水平、垂直敷设,其终端固定、吊线中间支撑应符合YD/T5138-2005《本地通信线路工程验收规范》图6.3.2-1、6.3.2-2 的要求。 ① 光缆以卡钩式沿墙敷设应在光缆上外套塑料保护管予以保护。 ② 应根据设计要求选用光缆固定卡钩,卡钩必须与光缆保护管外径相配套。 ③ 光缆卡钩间距为500mm,允许偏差±50mm。转弯两侧的卡钩距离为150~250mm,两侧距离须相等。同轴电缆卡钩垂直间距不大于1000mm。 17 2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司 1.3.7 引上光缆设计 (1) 本设计中引上保护管材质均为镀锌钢管、其规格为D108mm×4mm的镀锌钢管。 (2) 水泥杆上引上保护管的固定设计采用4.0mm镀锌铁线绑扎,墙壁引上管采用钢管抱箍及镀锌膨胀螺栓固定。引上管应在电杆上用4.0mm镀锌铁线绑扎两处(每处6圈,然后用撬棒两边紧固),绑扎上端距管口300mm,下端距地面400mm。 (3) 引上管要求地下长度为500mm,地面上长度为2500mm。引上管内设计敷设4根Φ34/28mmPE管,子管上端应伸出引上管口300mm。 (4) 引上管和手孔的间距小于1m时,设计采用在引上管铺砖保护,对大于1m的,设计采用从手孔敷设D108/4mmPVC塑料管或钢管和引上管对接,对接处的塑料管或钢管应用同材质的弯管头连接。 1.3.8 局内光缆 (1) 光缆敷设进入局(站)时应按设计规定的进局路由进入,进局光缆占用的管孔和在托架上的置放位置应符合设计和施工验收规范要求,光缆在托架上的摆放应整齐、不重叠、不交错,不上下穿越或蛇行;光缆在个转角的曲率半径应符合规定。 (2) 本工程都是基站接入光缆,进局(站)时,设计要求不更换为阻燃型光缆,采用原光缆程式直接进入各塔下屋基站为光缆。 (3) 设计要求光缆进局(站)后,应及时将所占用的管孔或孔洞封堵,架空光缆在进入塔下屋基站孔洞前必须作预留弯,以免雨水进入机房。 (4) 光缆由地下室或其他地下设施由爬梯引入楼上机房或基站时,应在爬梯横铁上用扎带予以固定,不能光靠最上层拐弯处受力固定。在同一楼层的槽道或走线架上敷设光缆时,一般将光缆平铺在槽道上,光缆需用扎带予以适当绑扎固定,光缆的绑扎应整齐、平直、不得相互交叉。光缆由槽道或地板引入综合机柜或DDF架时,也应予以固定在综合机柜或ODF的固定卡槽中。设计规定绑扎间距 不得大于50cm。光缆在上下走道和爬墙的部位,应垫以胶管,避免光缆受挤压。(5) 设计要求光缆拐弯时,其弯曲部分的曲率半径不小于光缆外径的15倍。 (6) 光缆在进线室、机房爬梯和槽道敷设时,应用光缆标志牌标明光缆的区间、建设时间、端别和程式。 18 2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司 (7) 在光缆易动、踩踏等不安全的部位,应对光缆作明显标志,如缠绕有色胶带等,提醒人们注意,避免外界损伤。 (8) 光缆进入光配线架,应首先按顺序予以固定在卡槽中,加强芯的固定要牢固连接在接地端子上。光缆接入光配线架或基站综合架的端子应按松套管及光纤的色谱顺序接入,并在子框的面板上标有本工程光纤的端子板图,尾纤的预留应按盘纤的顺序依次盘绕在盘纤盘中,并应及时做好标记。 (9) 光缆终端机房光配线架或基站综合机架都设有工作地线(电源地)和保护地线(屏蔽地)。光缆加强芯和光缆的屏蔽层设计要求一并应和光配线架(基站综合架)的保护接地端子相连接(光缆终端机房光配线架或基站综合机架至机房的保护接地线排间连接由设备侧负责连接)。 (10) 成端光缆。 ① 在设备机房的光缆终端接头安装位置应稳定安全,远离热源。 ② 成端光缆和自光缆终端接头引出的单芯软光纤应按照ODF的说明书进行走线并按设计要求进行保护和绑扎。 ③ 单芯软光纤所带的连接器,应按设计要求顺序插入光配线架(分配盘)。未连接软光纤的光配线架(分配盘)的接口端部应盖上塑料防尘帽。 ④ 软光纤在机架内的盘绕应大于规定的曲率半径。 ⑤ 光缆在光纤配线架(ODF)成端处,加强芯要可靠固定,将金属构件用铜芯聚氯乙烯护套电缆引出,并将其连接到保护地线上。 ⑥ 软光纤应在醒目部位标明方向和序号。 ⑦ G.655软光纤护套颜色一般为橙色或蓝色,G.652软光纤护套颜色一般为黄色。 1.3.9 光缆防护设计 1.3.11.1 防机械损伤 光缆的机械损伤防护主要依靠敷设时,要遵守操作规程,牵引长度和力度要符合相关敷设程序,光缆线路还应满足设计有关线路与其他建筑物的距离等。敷设后的光缆机械防护主要靠安全杆路的安全性。 (1) 管道光缆的防机械损伤 ① 敷设光缆时在人(手)孔角、管孔入口处、光缆牵引的转弯点、有高低差的人(手)处采用软管保护; 19 2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司 ② 敷设管道光缆时应涂抹中性润滑剂或液体石腊; ③ 光缆敷设完毕后。应堵塞管孔、子管孔,防止泥沙和鼠害。 (2) 架空光缆的防机械损伤 ① 敷设架空光缆时在电杆及电杆间、杆路的转角处、要装有滑轮,光缆的牵引头必须装有阻扭器; ② 敷设后的光缆机械防护主要靠安全杆路的安全性,在光缆接头处、隔一定的距离要作适当预留,有预留的光缆用预留架盘留,光缆过每根电杆处的微缩弯都采用光缆过杆保护管0.6m保护,穿塑管保护处不得绑扎。 1.3.11.2 防强电 (1) 本工程选用的光缆无铜导线,光缆内只有金属加强件,塑料护套耐压强度为15kV的光缆,设计并考虑将各盘光缆间的金属铠装层、加强金属件均在接头盒中作电气断开,将强电影响积累在单盘光缆制造长度内,光缆线路沿线不接地,仅在各局站内接地。 (2) 一般有与高压电力线平行时设计按表1.3-12的规定隔距考虑。本工程光缆路由大长度近距离平行高压电力线地段没有。可以忽略不计。 表1.3-12 光缆线路与高压电力线需保持的隔距 平 行 长 度 (km) 10 20 30 隔 距 (m) 电 力 线 电 压 220kV 土壤电阻率(Ω•m) 1000 100 500 20 43 100 290 230 520 650 450 3000 1000 140 680 1800 100 210 650 800 110kV 100 4 90 220 500 15 200 490 500kV 500 480 1500 2000 1000 680 210 2900 电信工程设计手册《长途光缆通信系统》表18.6 (3) 架空光缆线路在与电力线、广播线交越时,要采用三线防护绝缘夹板进行防护,防护长度应超出两边交越边缘各1m。 ④ 如果吊线敷设长度超过2公里,中间没有设计要求吊线每2公里左右做一次电气断开(采用绝缘隔电子连接吊线),当线路与电力线交越或多次穿过电力设施时,必须在交越处两侧做电气断开处理措施。 1.3.11.3 防雷 本工程光缆线路为市区地域,光缆线路未经过雷击区,工程设计在充分考虑 20 2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司 光缆结构特点的前提下,防雷保护措施主要是: (1) 要求除各局站外,沿线光缆线路的金属构件均不接地。 (2) 对光缆的金属构件接头处不作电气连通,各金属构件间也不作电气连通。 (3) 要求各局站内的光缆金属构件,应相互连通(金属加强芯和屏蔽层),并在综合机柜一起接到保护地线铜排上。 (4) 光缆线路路由设计按规范、相关规定与引雷目标保持应有隔距。 (5) 设计利用电杆拉线作避雷线。施工中利用电杆拉线作避雷线和接地线应按设计要求装设。 ① 水泥电杆的避雷线有预留避雷线穿钉和无预留避雷线穿钉的应符合YD/T 5138-2005《本地通信线路工程验收规范》中的3.6.2(1-2)的规定。 ② 在与10kV以上高压输电线交越处。两侧电杆上的避雷线应有放电间隙。其安装规格应符合YD / T 5138-2005《本地通信线路工程验收规范》中的3.6.2(3-4)的要求。 ③ 设计对角杆、跨越杆、终端杆及直线每隔8档左右的电杆都装置了拉线式地线,地线连通光缆吊线,通过拉线入地;由于所有的转角电杆都有拉线式接地线,因此非雷击区不再设置中间杆的接地地线。 1.3.11.4 防蚀、防潮 光缆外护套为PE塑料,并有铝塑粘结护层或钢塑粘结护层,具有良好的防 蚀性能。光缆纤芯套管内填充有石油膏,固不需再考虑另外的防蚀、防潮措施。1.4 光缆线路施工规范标准 1.4.1 器材检验 1.4.1.1 一般规定 (1) 应对建设单位送达的光缆及其它线路器材的规格、程式、数量进行签收,并与设计材料表的数量进行核对。 (2) 工程所用光缆及器材必须有产品质量检验合格证,厂方提交的产品测试记录。不符合标准或无出厂检验合格证的光缆和器材不得在工程中使用。 (3) 工程应经过检验的光缆及其它线路器材应做好相应记录。 1.4.1.2 光缆单盘测试 工程开工后,施工单位应会同监理单位在施工前对运到工地的光缆、硅管、器材的规格、程式、数量及出厂合格证进行检查,并做好记录(可以采取每批次 21 2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司 抽测形式)。光缆、光纤连接器应有传输特性参数的出厂测试记录。 (1) 单盘光缆检验:核对单盘光缆的规格、程式和长度应符合合同规定或设计要求,检查光缆外观有无损伤,填充物是否饱满,检查光缆出厂记录是否符合合同规定或设计要求,测试光纤衰减及长度。 (2) 光缆单盘检验时,应核对光缆外端的端别。光缆端别的确定应符合下列要求: ① 每盘光缆两端应密封和具有表示端别的颜色标志,一般A端标志为红色,B端标志为绿色。 ② 各线路工程的端别要求须满足设计文件的规定。 ③ 单盘光缆的光纤衰减系数测试应符合设计要求并与单盘出厂资料基本相符。 (3) 经过检验的光缆器材应作好记录,并在缆盘上标明盘号、外端端别、长度、程式(直埋、架空、管道及水下),以及使用段落(在配盘后标注)。 (4) 检验合格的光缆应及时恢复包装包括光缆端头的密封处理、固定光缆端头,光缆盘护板重新钉好,并将光缆盘置于妥善位置。 (5) 对于检验发现不符合设计要求的光缆、器材应及时登记上报不得随意在工程中使用,对光缆光纤个别损耗超出指标,应在重测后如确实超标,但超出不多并单盘光缆及中继段单纤平均损耗达标的可以使用。 (6) 光纤连接器应有良好的重复性和互换性,光缆接头盒及其附件应符合设计要求,应不漏气、不变形、不龟裂。 (7) 光缆接头盒及光缆终端盒检验主要指标请见表1.4-1。 表1.4-1 光缆接头盒及光缆终端盒检验主要指标 项目 光 缆 接 头 盒 光缆 终端 盒 密 封 性 能 光缆接头盒内充气压力100±5kPa,浸泡在常温的清水容器中稳定观察15min,应无气体逸出或稳定观察24h气压表指示无变化。 绝 缘 电 阻 光缆接头盒沉入1.5m 深的水中浸泡24h后,光缆接头盒两端金属构件之间、金属构件与地之间的绝缘电阻应≥20000 MΩ。 光缆终端盒两端金属 构件之间、金属构件 与地之间的绝缘电阻 应≥20000 MΩ。 耐 压 强 度 光缆接头盒沉入1.5m 深的 水中浸泡24h 后,光缆接 头盒两端金属构件之间、 金属构件与地之间在 15kV 直流作用下,1min 不击穿、无飞弧现象。 光缆终端盒两端金属构件 之间、金属构件与地之间 在15kV直流作用下,1min 不击穿、无飞弧现象。 22 2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司 1.4.1.3 其他线路器材的检验 (1) 水泥电杆 ① 环形钢筋混凝土电杆的结构应为锥形体,锥度为1/75。 ② 环形钢筋混凝土电杆有下列情况之一者不得使用: a 环向裂缝宽度超过0.5mm; b 有可见纵向裂缝的; c 混凝土破碎部分总表面积超过200mm2; (2) 水泥底盘、卡盘及拉线盘的程式及其偏差符合表1.4-2 要求。 表1.4-2 水泥底盘、卡盘及拉线盘的规定程式 名称 底盘 卡盘 拉线盘 程式(mm) 500×500×80 800×300×120 500×300×150 600×400×150 偏差(mm) 长、宽、厚±10 长、宽、厚±10 参考重量(kg) 46 73 44 69 YD/T5138-2005《本地通信线路工程验收规范》表2.4.3 (3) 镀锌钢绞线的规格应符合表1.4-3 规定。 表1.4-3 镀锌钢绞线的规格 公称截面积 钢绞线 每根/每股钢绞线 2(mm) 及股数 允许公差(mm) 50 7/3.0 ± 0.12 / ± 0.02 37 7/2.6 ± 0.12 / ± 0.02 26 7/2.2 ± 0.12 / ± 0.02 22 7/2.0 ± 0.12 / ± 0.02 18 7/1.8 ± 0.12 / ± 0.02 YD / T5138-2005《本地通信线路工程验收规范》表2.4.4 钢绞线外径 (mm) 9.0 7.8 6.6 6.0 5.4 拉断力(kg) (120kg/mm2 5460 4100 2930 2420 1920 (4) 塑料子管检验应符合下列要求: ① 塑料子管的材质、规格应符合设计要求。 ② 塑料子管的管身应光滑无伤痕,管孔无形变,其颜色、孔径、壁厚及其均匀度应符合设计要求,壁厚的负偏差应≤ 0.1mm。 1.4.2 光缆线路复测 (1) 线路复测应按施工图设计规定的路由上进行,遇特殊情况需改变路由时,应和建设单位、工地监理工程师协商,同时应通知设计人员。 (2) 架空杆路的复测,应依据施工图设计路由起始点至下一个转角的定标来取定该段的直线距离,再根据该段的实际地形逐杆按设计规定测量确定各个杆 23 2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司 位,正常情况下杆距宜为50m,允许偏差应小于20m。 (3) 管道光缆复测,管道光缆敷设前应按施工图设计对管道路由进行复测,丈量记录原有、新建管道人(手)孔间的准确长度,记录各手孔有无光缆接头盒或可能成为光缆预留盘放的手孔情况,并据此为光缆配盘做好准备。 (4) 敷设管道光缆的孔位应符合设计规定,敷设前必须清刷管孔。 (5) 敷设局内光缆前同样要先对光配线架位置进行确认,并和建设业主确认无误后,再按设计路由进行敷设。 1.4.3 立杆 (1) 挖杆洞前应校对该标桩位置是否与图纸或复测的记录相符,确认无误后方可挖洞,水泥杆洞宜为圆形或长方形。拉线坑应位于线路偏转角的平分线上,距高比应不小于1:1,当地形时距高比不得小于1:0.5,如距高比小于1:0.5,应改为吊板拉线。拉线坑应为矩形,洞(坑)底应平整,四壁应与底垂直。拉线地锚的实际出土点与规定出土点之间的偏移应≤ 50mm。地锚的出土斜槽,应与拉线上把成直线。拉线地锚应埋设端正,不得偏斜,地锚的拉线盘(横木)应与拉线垂直 (2) 电杆的洞深应符合表1.3-6的规定,土质的杆洞洞深偏差,应小于±50mm,30mm。 石质的杆洞洞深偏差应小于± (3) 在斜坡地区挖杆洞,其洞深应从洞的下坡口往下150~200mm计算洞深。 (4) 各种地锚的坑深应符合表1.3-8的规定,拉线地锚入土点的位置应合乎要求,地锚拉柄和拉线的配合应符合表1.3-9的规定。 (5) 石质土地锚的装设应符合地锚钢柄和拉线的夹角为90°的规定,其夹角5° 偏差允许± (6) 对线路偏转角大于45°时(角深为19.46m),应设置双终端拉线,每条拉线应分别装在对应的吊线张力的反侧,两条拉线应相互内移600mm,避免角杆发生歪斜的现象。 1.4.4 拉线 1.4.4.1 拉线上把另缠法、夹板法制作规格应符合表1.4-4的规定 表1.4-4 拉线上把另缠法、夹板法规格表 电杆 种类 水 拉线程式 1×7/2.2 缠扎线径 (mm) 3.0 首节长度 (mm) 100 24 间隙 (mm) 30 末节长度 (mm) 100 留头长度 (mm) 100 留头 处理 用1.5 2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司 电杆 种类 泥 杆 拉线程式 1×7/2.6 1×7/3.0 2×7/2.2 2×7/2.6 2×7/3.0 7/2.2 7/2.6 7/3.0 1块夹板 1块夹板 2块夹板 注:YD / T5138-2005《本地网光缆线路工程验收规范》表3.4.5-1 夹 板 法 缠扎线径 (mm) 3.0 3.0 3.0 3.0 3.0 首节长度 (mm) 150 150 150 150 200 间隙 (mm) 30 30 30 30 30 50 50 30 末节长度 (mm) 100 150 100 150 150 100 150 100 留头长度 (mm) 100 100 100 100 100 100 100 100 留头 处理 mm 钢线 另缠 5圈 扎固 1.4.4.2 拉线中把另缠法、夹板法制作把应符合表1.4-5的规定 表1.4-5 拉线中把夹、缠规格表 单位:mm 类别 夹、缠物类别 首节 间隔 末节 280 100 φ7夹板 1块 夹 230 150 φ7夹板 1块 板 100 100 φ7夹板 2块 法 中间隔30 7/2.2 100 330 100 3.0钢线 7/2.6 150 280 100 3.0钢线 7/3.0 200 230 150 3.0钢线 另 2×7/2.2 150 260 100 3.0钢线 缠 2×7/2.6 150 210 150 3.0钢线 法 2×7/3.0 200 310 150 3.0钢线 250 310 150 V型2×7/3.0 3.0钢线 注:YD / T5138-2005《本地网光缆线路工程验收规范》表3.4.11 拉线程式 7/2.2 7/2.6 7/3.0 全长 600 600 600 600 600 600 600 600 800 800 钢绞线留长 100 100 100 100 100 100 100 100 150 150 1.4.5 敷设光缆 (1) 应根据设计要求选用光缆挂钩程式 (2) 敷设管道光缆的孔位应符合设计要求。 (3) 光缆在杆上可作适当的伸缩预留,轻负荷区应每3~5杆作一处预留,预留在电杆两侧的挂钩间下垂25~30厘米,预留宽度一般2米,并套塑料套管保护。保护应符合YD/T5138-2005《本地通信线路工程验收规范》图6.1.5 要求。 (4) 应按照设计要求的A、B 端敷设光(电)缆。 (5) 敷设光缆时的牵引力应符合设计要求。 (6) 新建光缆接头处两侧光缆布放预留的重叠长度应符合设计要求。接续完成后光缆余长应在人孔内盘放并固定。 (7) 光缆标识牌、宣传牌 25 2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司 中国移动通信集团公司安徽有限公司网络部2008年10月对设置光缆宣传警示牌和悬挂光缆标志牌规定如下: ① 光缆宣传警示牌: a 直埋光缆宣传警示牌(800×600mm)原则上每公里设置2块,主要树立于村镇路口,对村、乡、镇及外来人群密集的地方可根据实际情况及设计要求适当增加。 b 直埋光缆宣传警示牌必须种植在直埋光缆上方,并明确管线路由走向。 c 光缆吊线式架空光缆的宣传警示牌(400×250mm)原则上每公里设置4块。 d 电杆固定式架空光缆的宣传警示牌(800×500mm)原则上每公里设置4块。 e 过路警示牌根据道路的具体情况而定,要求在车道正上方的架空跨路光缆上悬挂过路警示牌,并视道路大小可酌情增加警示牌数量。 f 超高车辆进出频繁的特殊路段如(货运场、停车场、沙石场等)及设计要求路段必须悬挂过路警示牌。 ② 光缆标识牌 a 每个人手井内的管道光缆必须分A、B端悬挂;架空光缆必须至少每隔3杆档分A、B端安装醒目光缆标识牌,接头、盘留处、转弯处必须悬挂。 b 架空光缆标识牌(80×60mm)原则按照每公里设置20块。 c 管道光缆标识牌(80×60mm)根据每个人(手)孔内光缆的根数来确定,每根光缆必须悬挂标识牌。 d 基站楼顶盘留光缆应绑扎光缆标志牌,基站内应分别在进线孔内、走线架上、综合机柜内三处挂光缆标识牌。 e 局内光缆预留20米,盘圈绑扎固定在进线室铁架或墙壁上,用光缆标识牌做好明显标识。 f 挂墙光缆必须挂光缆标识牌,每个转角处挂一个牌,直线处50~100米一个牌。 g 标识牌的规格、材质应一致,在施工敷设光缆前提供给施工单位。 h 光缆的预留杆、转角杆、过路杆、引上杆等处,必须设置标识牌,光缆标识牌应牢固绑扎在光缆上,并且字面应朝向宜看方向。 26 2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司 ③ 光缆预留架:设计不分新建或利用原有杆路,按每公里1.5块计列,其光缆预留长度应符合设计要求。 1.4.6 光缆的接续与接头盒安装 (1) 光缆接续前应检查接头盒是否符合合同的技术要求、附件种类、数量是否齐全。 (2) 光纤接续采用熔接法时,接续时应按光纤色谱顺序一一对应,并采用OTDR进行监测,使每根光纤的损耗符合要求。光纤熔接完成并测试合格后,应立即作增强保护措施,增强保护措施可采用热可缩套管法。 (3) 光缆的加强芯与接头盒的连接应牢靠,以保证有可靠的连接强度,为避免强电影响,加强芯不做电气连通。 (4) 光缆接续的环境应防尘、防潮。光缆接头坑应及时回填,防止接头盒受损。光缆接头盒应避免煤油等矿用油接近、接触,如有接触,应立即更换接头盒的密封圈,以保证接头盒的密封性。 (5) 光缆接续时应记录光缆接头盒接续两侧的计米码数,作为竣工技术资料。 (6) 光缆的纤芯应同号相接,不得错号。每个接头处,光缆与光纤都应留有一定的余量,以备日后维修或二次接续使用。 (7) 两端光缆的金属构件在接头处作电气断开。 (8) 光缆在局站终端,光纤编号应正确、正规、统一,尾纤盘绕应整齐美观。光缆加强芯与机房保护地线连通。 (9) 在光交接箱内的光缆引上孔处应有光缆标志牌,光纤应有对应光缆的光纤编号,空余的尾纤应整齐地盘绕在盘纤模块上。 (10) 光缆接续前应对光缆程式、接头位置并根据预留长度的要求留足光缆。 根光缆的端别核对光纤并编号作永久性标记。光纤接续应连续作业以确保质量。(11) 光纤熔接接续完成后应根据接头盒的不同结构,将余纤盘在光纤盘片内,其盘绕方向应一致。盘纤的曲率半径应符合相关规定要求;综合护套铝护层的连接应符合要求;光缆加强芯应按需要长度截断打弯,并按工艺要求固定在接头盒内电气断开。加强芯的连接应根据接头盒的结构加紧、夹牢,并能承受与光缆同样的拉力。光缆的损耗应符合设计要求。 (12) 光纤采用熔接法,每个中继段光纤损耗的平均值按不大于0.04dB/km,单个最大值不大于0.08dB/个考虑,光缆接续应严格按照相关规定执行。每个接头处, 27 2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司 光缆和光纤均应留有一定余长,以备日后维护所用。同时注意1550nm波长区对微弯损耗的敏感性,处理好接头。 (13) 光缆接头套管的封装应按工艺要求进行。封装完毕应测试检查并做记录,需要做地线引出的,应符合设计要求。 (14) 架空光缆接头盒的两侧光缆应做预留弯,两端的预留光缆应盘放在邻杆上的预留架上。 (15) 接头盒内应放入袋装防潮剂和接头责任卡,责任卡格式见下表: 表1.4-6 光缆接续责任卡 施工日期 施工单位 监理单位 接续人 监理人 备注 光纤 护套 年 月 日 时至 时 天气 温度 1.4.7 光缆的割接 1.4.7.1 割接前期准备 (1) 应对全部进出永安基站的光缆的成端位置、走向、预留及长度的情况按设计再进行一次核对,对ODF架上的纤芯占用情况进行核对,同时要对所有备用纤芯进行测试,并应保留测试记录; (4) 割接是否多次还需根据具体情况和上级的要求制定光路的割接顺序; (5) 割接人员的组织由实施单位上报,并获批准,检查割接工具的完好、检查测试仪表的完好,空闲纤芯的可用信; (6) 检查设备间的跳纤完好性,检查备用跳纤的数量是否充足; (7) 上报主管部门割接方案、拟定割接时间(一般为0点开始,宜在6点前完成)、割接人员组成等待批;根据上级的批准时间确定割接人员到达割接现场的时间。 (8) 了解割接点有关联的基站,及可能由于割接带来的影响; (9) 为保证传输基站间的业务尽量减少影响,要与网络维护部门确定割接时间,要求施工、线路维护地网密切合作,确保割接工作安全,顺利完成。 1.4.7.2 光缆割接 (1) 建设单位应对受影响的基站进行电路调配; 28 2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司 (2) 在机房成端前光纤进行光路对测,检查光纤连接是否正确,避免出现断纤、鸳鸯纤的现象; (3) 机房光缆进行开通测试。 (4) 根据割接或调整的方案按顺序依次进行。 (5) 各条光路光缆成端接续后,要经测试合格,再由网络维护人员将牌坊-众兴的光路改跳至永安,同时在传输机房应进行监测,测试检查成端接头处的光传输指标,确保割接点符合传输特性的要求。备用线应在全部接续完成后进行。 (6) 割接全部完成后,应清理现场,按规范按装好ODF成端,对预留的光缆做妥善处理,检查通信的恢复状况,核实设备的恢复是否正常,记录割开始接时间、完成时间,测试组应及时将测试资料存盘,报告现场指挥,确定割接完成后,方许撤离现场。 1.4.7.3 割接组织 应有现场指挥、割接组、设备组、测试组及后勤组组成。现场指挥和各小组具体人员应由割接实施单位确定并上报主管单位备案。 1.4.7.4 割接注意事项 (1) 对于一些材料的意外情况,应有一定的预计性。比如法兰盘、尾纤,这些材料必须充足,避免在关键时刻对割接造成影响; (2) 在机房的网管端的负责人必须时刻关注网管的报警是否正常(割接前及割接后),并且传输恢复后监控是否已经恢复,对整个割接的进程应该做到心中有数; (3) 在割接过程中可能造成的暂时的传输中断,对已开通的业务传输节点,应请建设单位作好应急和善后处理; (4) 建设单位的建维部门应有专人对整个割接的全过程进行现场配合,对割接光缆的环路的改变,需要在受影响的基站内跳纤或调整电路流向的站点应有维护部门的配合实施。 (5) 割接中的意外处理:如果在使用新纤芯后,传输业务不能正常,应以最快速度检查个跳纤环节,检测传输质量,尽快解决问题,避免业务受到更大影响。 1.4.7.5 割接实施的准备 (1) 各作组各自准备好各自的仪表、工具; (2) 各工作组应提前到达现场,测试组应在出发前对将使用的仪表要进行通 29 2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司 电检查,并做好割接准备工作,接续前熔接机应进行放电试验,接续过程要仔细,按照预定纤序进行; (3) 机房测试人员对割接光缆进行测试并记录,在收到割接负责人的割接通知后,接头组人员才能中断光缆进行割接; (4) 光缆接续采用边割接边测试的方法,按照预定纤序熔接,接续完成后,经测试合格,才能对接头封焊; (5) 各小组成员要服从统一指挥,作好充分准备,要认真、谨慎,严格按照操作规程进行; (6) 检查新敷设的光缆与原光缆型号的一致性,接续时按色谱熔接; (7) 测试人员到达机房后,记录ODF架上光纤端子、色谱排列顺序、核对光缆测试资料,并将色谱排列顺序通知接续组; (8) 光缆割接前,向网管确认可以割接,才可以通知割接开始; (9) 标签纸必须在光缆固定在接头盒前贴到线束上,以免在光缆固定后做出错误判断; (10) 光缆的割接必须在帐篷或车厢内进行; (11) 割接完毕后,必须经监控中心确认电路的恢复,并将割接开始、完成时间上报监控中心。 (12) 割接工具,光纤熔解机、OTDR、光纤切割刀、光缆接续车、光话机、电源、光功率计、双头尾纤、标签纸、照明灯、电筒、电源插板、酒精,基站机房钥匙或门卡、车辆。 (13) 割接材料,割接需要的材料包括:热缩套管、法兰盘、尾纤、接头盒1套(原有接头盒开封后利旧)等,必须留有一定的余量。 1.4.8 光缆程式及光缆验收标准 1.4.8.1 本工程光缆主要采用管道及架空方式敷设,其型号主要为GYTA-24B1和GYTA-12B1光缆。 1.4.8.2 有关光纤光缆主要技术要求及指标应满足中国移动通信集团安徽有限责任公司招标文件中的技术规范要求。工程施工前,施工单位应严格按照相关技术要求对相关指标进行单盘检验及验收。 1.4.8.3 光缆验收标准 (1) 中继段测试要求:B4光缆只进行1550nm窗口测试,城域传送接入网光缆 30 2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司 只进行1310nm窗口的测试。 (2) 光缆中继段测试的内容应包括: ① 线路衰减; ② 向散射信号曲线; ③ PMD链路值。 (3) 中继段衰减和PMD链路值的测试结果应符合以下要求: ① 光纤衰减测试应取双向测量平均值; ② 测量的光纤衰减平均值和PMD链路值,必须符合中国移动通信集团安徽有限责任公司《光缆线路工程施工验收技术规范》的要求。设计结合YD 5102-2010《本地通信线路工程设计规范》及YD/T 5121-2010《本地通信线路工程验收规范》,制定本工程光缆测试指标,指标值请见表1.4-7、1.4-8: 表1.4-7 B4光纤衰减平均值和PMD链路值 指 标 备 注 ≤ 0.26dB/km 缆内光纤衰耗平均值为:0.22dB/km 2km盘长 1 损耗值 3km盘长 ≤ 0.25dB/km 光缆接头损耗双向平均值≤ 0.08dB/个 2 80% 0.1ps / km 1/2 PMD链路值 此指标城域传送网工程可不进行测试 中国移动通信集团安徽有限公司网络部关于《光缆线路工程施工验收技术规范规定》2007年9月 表1.4-8 B1.3光纤衰减平均值和PMD链路值 备 注 2km盘长 缆内光纤衰耗平均值为:0.22dB/km 1 损耗值 3km盘长 光缆接头损耗双向平均值 ≤ 0.08dB/个 80% 0.15 ps / km 1/2 PMD链路此指标城域传送网工程可 2 1/2100% 0.20 ps / km 值 不进行测试 中国移动通信集团安徽有限公司网络部关于《光缆线路工程施工验收技术规范规定》2007年9月 序号 项目 指 标 ≤ 0.26dB/km ≤ 0.4dB/km (1550nm) (1310nm) ≤ 0.25dB/km ≤ 0.39dB/km (1550nm) (1310nm) 序号 项目 ③ 测试结果应做详细纪录 (4) 中继段光纤后向散射信号曲线应符合下列要求: ① 信号曲线无异常; ② 全程信号曲线应打印纪录或拍照。 1.4.9 光缆的预留 (1) 各局站光缆预留不多于20m,预留光缆应盘放好并固定; (2) 管道光缆每隔500m左右的人(手)孔、接头处两端相邻的人(手)孔及 31 2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司 引上处各需预留8~10m; (3) 架空光缆每隔500m左右的电杆处、架空光缆接头两侧电杆处需各预留8~10m,一般预留架按1.5个/km计列; (4) 架空光缆在过主要大桥、大河时要作适当的预留; (5) 架空光缆在过主要公路(国道、省道)时要作适当的预留,在跨越主要县道时,也要作适当的预留; (6) 光缆的预留请参照表1.4-9执行: ① 光缆在接头处的预留长度应包括光缆接续长度,光纤在接头盒内的盘留长度以及光缆施工接续时所需要的长度等。光缆接头处每侧预留长度如表1.4-9所示: 表1.4-9 光缆预留长度表 序号 1 2 3 4 5 6 项 目 自然弯曲增加长度(米/公里) 人孔内弯曲增加长度(米/人孔) 接头每侧预留长度(米) 设备每侧预留长度(米) 光缆过电杆伸缩弯增加长度(米) 光缆预留长度 管道光缆 5 0.5~1 ≤ 30(注1) ≤ 15(注2) 10~30(注3) 架空光缆 5 10~15 10~20 0.3~0.4 1、其他预留 按设计要求 2、部分工程 可根据实际 情况按设计 要求预留 备 注 光缆穿越河流、公路、跨越桥梁时,5~30 光缆在两侧手孔内各预留长度(米) 注1:采用气吹法敷设光缆的光缆预留长度。 注2:采用人工牵引法敷设光缆的光缆预留长度,市区段落的光缆在接头井两侧的井中预留。 注3:通信机房有进局地下室,光缆预留长度20~30米,通信机房无进局地下室,光缆预留长度15米。 中国移动通信集团安徽有限公司网络部关于《光缆线路工程施工验收技术规范》2007年9月 ② 管道光缆每个人(手)孔中弯曲的预留长度为0.5 m~1.0m;架空光缆可在杆路适当距离的电杆上预留长度。 ③ 局内光缆可在进线室内预留长度不大于20m 或按实际需要确定,预留光缆不得置放在进线室的槽道架上。 (7) 光缆敷设安装必须严格按YD 5137-2005《本地光缆线路工程设计规范》和YD/T 5138-2005《本地光缆线路工程验收规范》执行。竣工测试资料应齐全,特别是1550nm和1310nm波长区中继段衰减测试记录和中继段后向散射曲线记 32 2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司 录。光缆线路各项指标必须满足设计及系统要求。 (8) 光缆配盘要求 ① 光缆配盘一般时在工程路由复测、单盘检验之后,分屯敷设之前进行。② 光缆按实际到货盘长考虑配盘,合理分配不同盘长光缆。尤其是长段、短段光缆的合理配盘,尽量将光缆的接头点安排在基站接入光缆的引入点,尽量减少光缆接头数量。 ③ 光缆配盘应考虑将接头位置避开水塘、河流、以及道路等不宜接头的地点。管道接头应避开多个接头设在一个人(手)孔内,管道光缆和架空光缆的接头尽量考虑在架空位置上。 ④ 光缆配置应按规定预留长度,避免浪费,单盘长度选配应合理,尽量节约光缆,为维建设单位多留一些余料作以后维护用,同时又降低了工程造价。 ⑤ 根据光缆随缆记录及验收测试记录,应将模场直径靠近及同心度好的光缆配置在一起,避免将光纤模场直径为偏差正负极限的光缆放在一起。从而减小光纤接头的衰耗,以达到或优于设计验收指标。 ⑥ 光缆配盘时应使配盘的中继段长度接近设计长度,并将光缆接头及其他预留长度、自然弯曲增长量等考虑在内。架空光缆自然弯曲量按20‰考虑;管道按15‰;同时考虑到其它因素,综合取定中继段预留光缆按30‰考虑。 ⑦ 配盘时要充分考虑避免将管道光缆接头安排在十字路口、分歧拐弯人孔、及光缆接头多的人孔内。应选择便于维护和施工及安全的人孔内。 ⑧ 施工单位复测后应编制中继段光缆配盘图,禀报监理工程师审核签字确认。 1.4.10 光缆编制 光缆编制应以便于施工管理和今后维护为原则,本设计安排如下:由原接入段接入的按原敷设的端别执行,新建的支线段一律按接出站为A端,接入站端为B端。 1.4.11 光缆的分屯及运输 (1) 应根据光缆的配盘或复测的有关数据、资料制定合理的分屯及运输计划,尽量减少光缆盘滚动的距离; (2) 运输光缆盘时,不得使光缆盘处于平放位,不得堆放;运输车辆上的光缆盘应予固定绑扎,防止冲撞。光缆卸放严禁将光缆盘从车上直接推下防止光缆 33 2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司 撞伤; (3) 光缆的贮存中应防止受潮和长时间暴晒,并应防止冲撞、挤压和任何机 械损伤;滚动光缆盘时,应按光缆盘上的转动箭头方向进行,不得作长距离滚动。1.4.12 工程竣工及验收 (1) 工程竣工后,工程竣工应满足《中国移动通信集团安徽有限公司通信工程验收管理办法》的相关要求,施工质量检验和竣工验收技术标准执行中华人民共和国通信行业标准YD/T5138-2005《本地通信线路工程验收规范》和设计文件的标准要求进行验收。施工单位在验收前,应将工程竣工技术资料一式5份送交监理单位、建设单位或验收小组,同时应提交竣工文件电子档。 (2) 监理检验和竣工验收 ① 光缆线路工程的监理检验按表1.4-10、1.4-11表的项目内容进行,隐蔽工程经监理工程师验收一般不再重验,其余项目的验收一般应按表1.4-12所列项目和内容进行。 表1.4-10 管道光缆工程监理检验项目内容表 序号 内容 检验方式 1 光缆规格 监理检验 2 光缆管孔位置 监理检验 3 护缆膨胀塞或PVC胶带缠绕 监理检验 4 光缆敷设质量 监理检验 5 预留光缆垂度及盘放 监理检验 6 光缆接续质量及接头盒安装、保护 监理检验 7 人(手)孔内光缆的保护措施 监理检验 中国移动通信集团安徽有限公司网络部关于《光缆线路工程施工验收技术规范》2007年9月 表1.4-11 架空光缆工程监理检验项目内容表 检验方式 光缆规格 监理检验 挂钩卡挂间隔 监理检验 光缆引上挂钩、质量(包括地下部分) 监理检验 光缆敷设质量及光缆垂度 监理检验 预留光缆盘放质量即曲率半径 监理检验 光缆接续质量及接头盒安装、保护 监理检验 与其他设施的间距即保护措施 监理检验 中国移动通信集团安徽有限公司网络部关于《光缆线路工程施工验收技术规范》2007年9月 表1.4-12 光缆工程竣工验收项目内容表 序号 1 2 3 4 5 6 7 内容 34 2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司 序号 内 容 及 规 定 1 管道光缆抽查的人孔数应不少于人孔总数的10%; 2 人孔内:光缆盘留绑扎、挂放标识牌、接头盒固定、使用护缆塞、光缆保护等; 管道光缆1 3 地下室:光缆盘留、爬梯和走线架绑扎、进线孔封堵、挂放标识牌安装工艺 等; 4 光缆成端:盘留、标识、接地、保护,满足尾纤安全要求等 5 宣传牌、标识牌、警示装置、人孔编号是否满足设计要求。 1 架空光缆抽查的长度应不少于光缆全长的10%; 2 沿线杆路与其他设施间距、预留光缆盘放、与其他线路交越、靠近地段的防护措施等; 架空光缆2 3 地下室:光缆盘留、爬梯和走线架绑扎、进线孔封堵、挂放标识牌安装工艺 等; 4 光缆成端:盘留、标识、保护,满足尾纤安全要求等; 5 宣传牌、标识牌、警示装置、电杆编号是否满足设计要求。 1 中继段光纤线路衰减竣工时应每根光纤都进行测试;验收时抽测应不少于光纤芯数的25%; 2 中继段光纤后向散射信号曲线竣工时应每根光纤都进行检查;验收光缆主要3 时抽查应不少于光纤芯数的25%; 传输特性 3 接头损耗的核实,应根据测试结果结合光纤衰减检验; 4 PMD链路值竣工时应该每根光纤都进行测试;验收时抽测应不少于光纤芯数的25%。 中国移动通信集团安徽有限公司网络部关于《光缆线路工程施工验收技术规范》2007年9月 项 目 (3) 竣工验收资料应包括: ① 工程验收前施工单位向建设单位提交竣工技术文件一式5份。 ② 提交的竣工技术文件应包括下列规定资料: a 工程竣工图纸:利用原施工图纸改绘,个别变动甚大或原设计施工图已无法改绘时,应重新绘制; b 建筑安装工程量总表; c 工程说明; d 开工报告; e 停(复)工通知(根据实际情况编制); f 交工通知; g 已安装线路明细表; h 工程变更单; j 随工质量检查记录:全部工程中的隐蔽工程签证; k 重大工程质量事故报告表(根据实际情况编制); l 交接书; 35 2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司 m 验收证书(空白); n 测试记录,包括光缆配盘图。图表式样见(YD/T 5138-2005 P38~P45)表11.3.3-1~表11.3.3-12。 (4) 竣工技术文件应符合下列要求: ① 内容齐全:应符合部颁施工验收办法和要求,文件资料齐全。 ② 准确:竣工图纸,测试记录应图纸与实际相符、数据正确。 ③ 清楚:资料的誊写应清楚。 (5) 工程竣工图 ① 工程竣工图纸应包括光缆路由图、杆路编号顺序图、光缆结构图、光缆敷设图(包括管道段长、管孔占用图、管道断面图、杆距、电杆程式、光缆程式、光缆预留位置(注明人孔编号或电杆编号)、光缆预留长度(以光缆外护套尺码登记)、光缆端别; ② 进局机房光缆敷设图(光缆路由、走向、槽道长度),ODF端子占用图(面板图、子框位置图、占用端子图); ③ 光缆竣工测试记录(单盘光缆光纤衰减统计表、光纤接头损耗测试记录表、光纤线路衰减测试记录表等); (6) 其他验收项目及内容应按部颁《原邮电部通信建设工程竣工验收办法》和本规范或设计要求执行。 1.5 需要说明的其他问题 (1) 过主要公路(国道、省道)、桥梁、河渠、船闸、铁路以及在城镇内新建杆路等事宜,需请建设单位或施工单位在杆路复测定位后,进一步与相关部门联系,落实取证(书面),以便工程顺利施工,避免因路由不符合乡镇规划而引发返工、浪费材料和延误工期的现象。 (2) 线路工程的设计、施工受外界环境条件影响较大,施工过程中由于设计勘察时间和施工时间的差别,可能会出现路由环境的变化,由此引起部分设计路由的变更和更改,施工单位应作好更改记录,请工程监理单位做好变更签证,以保证工程竣工资料的准确性。 (3) 光缆敷设前应根据单盘测试后的盘长进行配盘,并对设计配盘材料进行核对,以便光缆的配盘和施工的顺利;若有路由发生变更,请根据变更后的长度重新进行配盘。 36 2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司 (4) 本工程建设单位特别规定,杆路跨越省县道公路,要求吊线距地面的高度为6.5m,杆路跨越乡级公路要求吊线距地面的高度为5.5m,设计中对过路杆高作相应配置,请施工单位在复测中也按上述要求配置过路的电杆程式。 (5) 本工程设计勘察时有个别基站未能进入,未取得原有机房查勘机架ODF占用情况,施工时请对照实际情况进行光缆的终端及分布排列。 (6) 线路施工经常和道路、其他通信线路、强电线路交越,请施工队伍做好安全生产计划措施,并应上报建设业主备案,同时监理工程师应做好安全生产的监理事宜。 (7) 本工程光缆附挂原有杆路,施工时务必确保原有光缆的安全。 2 预算 2.1 预算说明 2.1.1 工程概况 2012年第15批综合覆本工程是2012年合肥用户光缆网线路工程一阶段设计: 盖系统接入光缆线路单项工程(铁通合作建设)。本工程共接入中铁四局办公楼、 37 2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司 投资大厦、出版传媒集团、枫丹城市花园、国轩苑、翰林府邸2号楼、翰林雅居光交接箱、澜溪镇小区、月桂苑光交箱、安广科技专修学院南校区、锦绣年华、治安大队主干、省、、翰林府邸、翰林府邸2号、交通学院南区、汇林园小区、华润纺织厂、元一名城A区17#电梯机房、安粮钢材大市场光交箱、民航家园、商旅学校、碧雨新村、安徽省教育厅、雅迪商务会所、香樟花园48栋604室、新泉家园、省立医院综合楼、新华优阁主干覆盖等28个接入点。 本工程勘察总长为29.181公里,附挂电力杆路光缆0.979公里,架设架空8芯光缆0.368公里,架设架空12芯光缆0.156公里,架设架空24芯光缆0.611公里,架设架空48芯光缆0.1公里,架设架空72芯光缆0.368公里;敷设8芯管道光缆4.084公里,敷设12芯管道光缆4.588公里,敷设24芯管道光缆5.768公里,敷设48芯管道光缆2.258公里,敷设72芯管道光缆1.205公里;敷设吊线式墙壁光缆16.99百米;管内穿放光缆15.34百米;桥架内明布光缆36.61百米。光缆线路传输长度为33.84公里。 2.1.2 工程类别 依据《依据建设工程类别划分标准》本工程为三类通信建设工程。 2.1.3 预算及技术经济分析 (1) 预算总投资 本单项工程预算总投资为904398.5元,技工工日:2156.07个,普工工日1175.57个。 (2) 技术经济分析 技术经济分析请见工程预算总投资和单位造价表: 表1.1-2 工程预算总投资和单位线路公里造价表 项 目 光缆线路长度 总投资 单位造价 单位造价 单 位 公里/纤芯长度 元 元/线路公里 元/芯公里 指 标 33.84/590.042 904398.5 26725.72 1532.77 本单项工程预算总投资904398.5元,光缆线路纤芯总长度为590.042芯公里。2.1.4 预算编制依据 (1) 工信部规〔2008〕75号“关于发布《通信建设工程概、预算编制办法》及费用定额”。 38 2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司 (2) 工信部2008年5月发布的《通信建设工程概算、预算编制办法》。 (3) 工信部2008年5月发布的《通信建设工程费用定额》。 (4) 工信部2008年5月发布的《通信建设工程施工机械、仪表台班费用定额》。 (5) 工信部2008年5月发布的《通信建设工程费用定额》《第四册 通信线路工程》。 (6) 原信息产业部信部规〔2000〕1219号文《关于发布通信工程建设监理费计费标准规定(试行)的通知》。 (7) 原信息产业部(信规函)〔2003〕13号文《关于通信线路工程中电缆、光缆费用计列有关问题的通知》。 (8) 2010年合肥分公司传输管线工程设计单位入围结果的通知。 (9) 本工程设计图纸。 2.1.5 编制办法 本工程预算根据原邮电部2008年5月颁布的《通信建设工程概算、预算编制办法及费用定额》等有关文件编制。 2.1.6 有关费率、费用及单价的取定 (1) 本工程按三类工程计取相关费用。 (2) 省公司2008年6月发布的材料指导价。 (3) 表二税金基数中光缆费用已从中核减。 (4) 工程仪表使用费按技工费的4%计取。 (5) 表四中的供销部门手续费、运杂费及运输保险费不予计列。 (6) 工程监理费项目取定费率为4%。 (7) 光缆中继段测试工程量按照每个接入点光缆为一个中继段考虑。 (8) 根据安移动采购〔2007〕53号“关于发布集团公司2007年光缆接头盒中标结果及分配的通知”,本工程光缆接头盒12芯、24芯均采用国产接头盒(无锡东旭),48芯以上采用进口接头盒。 (9) 地锚用警示保护管每处按0.5米计,斜拉线警示保护管按每处按2米计,此保护管仅在市区、城镇、路边使用。 (10) 引入段管道综合赔补费按市政道路破复管道表格计列。 (11) 本工程光缆所有架挂电力杆路的均由电力施工单位施工,施工费按11500元/km计列,施工费用包括架空所需材料(如钢绞线、电缆挂钩等材料), 39 2012年第15批综合覆盖系统接入光缆线路单项工程(铁通合作建设)一阶段设计 安徽福通公司 预算中将不再计列架相应的工作量和铁件等材料。另外考虑到架挂电力杆路部分光缆均由供电部门施工单位施工的特殊性,列支800/km的施工协调费。 (12) 市区综合覆盖系统光缆接入协调费按800元/处计列,三县综合覆盖系统光缆接入协调费按600元/处计列。 (13) 根据建设单位要求,微控定向钻顶管材料均采用硅芯管,施工费用按4根硅芯管折合一根PVC管计列。 (14) 设计费计算依据2011年合肥分公司传输管线工程设计单位入围结果及取费标准,计算方法如下: 本工程光缆勘察长度为29.181公里,工程费704111.14元,附挂电力杆路施工费11258.5元,微孔定向顶管221米。 设计费计算如下:(29.181公里×900元/公里+704111.14×4.5%)×0.5+221×18元=32952.00元。 2.2 预算表格编号 表2.2-1 预算表格编号 序号 1 2 3 4 5 6 7 8 9 10 名称 工程预算总表(表一) 建筑安装工程费用预算表(表二) 建筑安装工程量预算表(表三)甲 建筑安装工程量预算表(表三)甲 建筑安装工程机械使用费预算表(表三)乙 建筑安装工程机械使用费预算表(表三)丙 国内器材预算表(表四甲)(需要安装设备表) 国内器材预算表(表四甲)(国内材料表) 国内器材预算表(表四甲)(国内材料表) 工程建设其他费用预算表(表五)甲 编号 FT2012Y001-01 FT2012Y001-02 FT2012Y001-03 FT2012Y001-04 FT2012Y001-05 FT2012Y001-06 FT2012Y001-07 FT2012Y001-08 FT2012Y001-09 FT2012Y001-10 40